Lokasi konstruksi yang menunjukkan alat berat dan puing-puing dari pembongkaran pabrik lama NETZSCH Pumps & Systems di Waldkraiburg.

22.04.2024

Tantangan Emosional & Logistik: Pembongkaran Pabrik Lama NETZSCH I di Waldkraiburg

Setelah 270 hari kerja intensif, pekerjaan selesai: Pabrik lama I di Liebigstraße di Waldkraiburg, simbol sejarah perusahaan NETZSCH Pumps & Systems yang sukses, telah diratakan dengan tanah untuk selamanya. Pemindahan ke Kampus NETZSCH yang baru di Geretsriederstraße 1 di Waldkraiburg berlangsung pada awal tahun 2023.

The process was a logistical challenge and very emotional for many people. Both current and former employees who had worked at the plant for decades and neighbouring residents watched with keen interest and melancholy as the building was demolished piece by piece by the company Bock & Söhne GmbH.

Pembuangan limbah konstruksi yang ramah lingkungan

Plant I, NETZSCH, Pumps, Systems, Demolition
Countless excavators, lorries and other heavy equipment were on site during the demolition of the halls and office buildings.
Lokasi pabrik NETZSCH Pumps & Systems yang telah dibongkar di Waldkraiburg, menunjukkan puing-puing dan alat berat untuk pembuangan limbah yang ramah lingkungan.
NETZSCH Pumps & Systems telah berproduksi di lokasi di Liebigstraße di Waldkraiburg sejak tahun 1961.
Excavator menghancurkan pabrik lama NETZSCH di Waldkraiburg, menunjukkan proses pembuangan limbah yang hati-hati dan ramah lingkungan.
Untuk memastikan pembuangan yang ramah lingkungan, puing-puing dan limbah lainnya dibuang secara terpisah.

Plant I, which covered an area of 16,500 m², generated a huge amount of rubble during the demolition. The individual parts of the building were removed with the utmost care and precision. A total of around 15,000 tonnes of demolition material and waste was produced. In addition to the construction waste, there was various other waste, such as insulation materials, plaster, wood, metals, glass and fluorescent tubes. The professional recycling of this large amount of waste was an immense challenge. To cope with this, around 1,200 lorries were used, transporting the waste to specialised waste disposal companies and thus ensuring environmentally friendly disposal.

After 270 days, the time had come – the old plant was finally a thing of the past. New projects will be developed on the now empty site in the future. Plant I will only live on in the memories of its employees.